This week the house has been sitting idle. Internal plumbing was completed, but the outside gas outlet was installed on the wrong side of the alfresco. A call to the SS and this was promptly fixed at the end of the week.
Bricks have been delivered, but the brickies are still working on another job so now we wait. Hoepfully they will start soon.
Saturday, 29 September 2012
Tuesday, 18 September 2012
Roof framing complete and windows installed
Today the last part of the roof was erected, which means the framing stage is now complete. Today the windows must have been delivered and this afternoon they were instaling the windows and expected to be finished by the end of today. Windows are Anodic off white, which should hopefully have a nice contrast with our bricks.
The bricks are due to delivered early next week.
The bricks are due to delivered early next week.
Saturday, 15 September 2012
Second floor framing
The second floor framing was started this week. Did our first walk through and very happy with the size of the rooms. Our walk in pantry is huge, storeroom is also big, going to love having a lot more storage space.
Drove by this afternoon and a tradesman was there doing some more work on the frame. Roof has also been delivered so that should be completed early next week.
Front of the house
Walk in pantry
Dining room - stairs will be on the right, alfresco on the left
Leisure room
Laundry
Back of the house and pool
Main bedroom
Main bathroom
Upstairs lounge
Hallway to the main bedroom and front balcony
View down the street from the front of the house. Roof frames below.
Drove by this afternoon and a tradesman was there doing some more work on the frame. Roof has also been delivered so that should be completed early next week.
Front of the house
Alfresco
Back of the house
KitchenWalk in pantry
Dining room - stairs will be on the right, alfresco on the left
Leisure room
Laundry
Back of the house and pool
Main bedroom
Main bathroom
Upstairs lounge
Hallway to the main bedroom and front balcony
View down the street from the front of the house. Roof frames below.
Wednesday, 12 September 2012
Framing has started
Today the builder started on the frames. First floor nealy complete. Pretty happy things are still progressing well. We can now have a bit of an idea of room sizes.
Tuesday, 11 September 2012
External plumbing done
Drove by the block today and found the external plumbing was completed yesterday.
Plus we now have a big pile of dirt at the back of the house and the front. Hmmm, not sure if we can utilise that for fill. I'm sure there will be growing pile of something as the build progresses.
Our SS contacted us late last week, after external plumbing, the next item on the list to be completed is the frame.
Plus we now have a big pile of dirt at the back of the house and the front. Hmmm, not sure if we can utilise that for fill. I'm sure there will be growing pile of something as the build progresses.
Our SS contacted us late last week, after external plumbing, the next item on the list to be completed is the frame.
Tuesday, 4 September 2012
We have a slab!!
Another day, this time we have a slab! Can't believe how much work has been completed, this time last week we had a scapped site, 4 work days later we have a slab.
Monday, 3 September 2012
Formwork
Today the builders were back on the block completing the formwork. Looks like we are ready for the concrete slab.
Subscribe to:
Posts (Atom)
Labels
Air conditioning
(1)
Bathroom
(5)
Bricks
(7)
Carpet
(2)
Cornice
(1)
Doors
(3)
Driveway
(2)
Electricals
(1)
Eves
(2)
External colours
(1)
Facia
(1)
Formwork
(1)
Frame
(2)
Garage door
(1)
Guttering
(1)
Gyprock
(2)
Hallway
(1)
Home theatre
(2)
House plans
(1)
Internal Colours
(1)
Kitchen
(8)
Laundry
(3)
Laundry landing
(1)
Letterbox
(1)
Lights
(2)
Pantry
(1)
Pavers
(1)
Piering
(1)
Plumbing
(2)
Pool
(7)
Roof
(2)
Salinity
(1)
Screen door
(1)
Shower screens
(1)
Shutters
(2)
Site cut
(1)
Slab
(1)
Stairs
(5)
Steps
(1)
Taps
(1)
Tiles
(5)
Tiling
(3)
Water tank
(1)
windows
(1)
WIR
(1)